Nearly two years of deliberation, negotiation and preparation at an end, repaving in the Edgelea subdivision begian in earnest this week with milling and asphalt work on multiple streets. On Tuesday morning, a crew on Fairway Drive had a milling machine (above) literally chewing up and spitting out the old, broken-down pavement before a second group of workers came through laying down hot mix asphalt (right). Wabash Valley Asphalt was awarded the $1.5 million project that will repave the 2.8 miles of road in the subdivision as well as improving drainage in certain trouble spots.