Work in Progress

Tuesday, August 16, 2016
Banner Graphic/ERIC BERNSEE Despite wet pavement from more rain in Greencastle Tuesday morning, Grady Brothers Inc. began milling work on Shadowlawn Avenue through the Deer Field Estates Subdivision as part of the City of Greencastle's summer street resurfacing project. Milling work later occurred Tuesday on Terrace Lane as well in preparation of resurfacing. Work will continue, weather permitting, as follows: Aug. 22-26, Washington Street from Percy Julian Drive to Wood Street, for installation of underdrain, deep milling of soft spots, installation of new base and resurfacing; Aug. 22 and 26, Hanna Street, Locust to Bloomington, for milling and resurfacing; and Aug. 29-31, Calbert Way, milling, repair of soft spots and resurfacing.